City Engineering Department Construction Project Updates
City Hall - 333 W. Ellsworth Midland, MI 48640 Phone: 989-837-3348 Email:
lself@midland-mi.org
STREET RESTRICTIONS FOR CONSTRUCTION
CURRENT AS OF : 10/06/2025 at 06:23:44
LAST UPDATE: 10/03/25 at 03:14 PM
ALL CONSTRUCTION UPDATES FOR 10/03/25 APPEAR IN RED
CONTINUING CONSTRUCTION
Omni Fiber - New Fiber Installation
Project Description: Omni Fiber is working to bring high-speed fiber internet to Midland. This project will begin at the end of March 2025 and has an estimated completion date of December 2026.
Residents can expect so see flags from MISS DIG marking underground utilities, as well as equipment and crews working in outlawns. Temporary lane closures in the street may be possible. Disturbed outlawns will be restored once underground utility activity has been completed.
1. Wheeler St (1711 Wheeler to 1012 Wheeler)
2. Swede Ave (4701 Swede to 5312 Swede)
3. Blakely St (Swede to 1806 Blakely)
4. Vine St
5. Avalon St (Swede to Claremont)
6. Winchester Dr (Avalon to Claremont)
7. Winchester Ct
8. Claremont St (Wheeler to Winchester Dr)
9. Peppermill Circle
10. Shoal Creek Circle
11. Settlers Passage
12. Whispering Oak Dr
13. Whispering Oak Circle
14. Foxpoint Circle
15. Redfern Circle
Please contact Omni Fiber with any questions or concerns: (844) 844-6664
Detours/Traffic Control: Possible lane shifts/closures.Project Status: In progress - Currently working on Love, Lancaster, Wallen, Dartmouth & Airfield Ln.Est. Completion Date: December 31, 2026
Ripple Fiber - New Fiber Installation
Project Description: Ripple Fiber is working to bring high-speed fiber internet to Midland. This project will begin at the end of March 2025 and has an estimated completion date of December 2026.
Residents can expect so see flags from MISS DIG marking underground utilities, as well as equipment and crews working in outlawns. Temporary lane closures in the street may be possible. Disturbed outlawns will be restored once underground utility activity has been completed.
Ripple Fiber will begin their first area of construction at 1125 E. Haley St. through 704 S. Saginaw Rd.
Please contact Ripple Fiber with any questions or concerns: (734) 251-2744
Detours/Traffic Control: Possible lane shifts/closures.Project Status: In progress - Currently working on Jefferson, Lancaster, Sugnet, Ashman & Hollybrook.Est. Completion Date: December 31, 2026
2025 JEFFERSON AVENUE RECONSTRUCTION & WATER MAIN
Project Description: This project is for the street reconstruction and water main installation on Jefferson Ave. from Lyon Rd. to Ashman Circle. The project scope includes, but is not limited to crushing & shaping of bituminous pavement, storm sewer modifications, removal/replacement of concrete curb and driveway approaches & placement of new bituminous pavement and installation of water main.Detours/Traffic Control:Project Status:Punch list in progress.Est. Completion Date: September 20, 2025
2025 CRUZ DR., JAMES DR. & WILLARD ST. RECONSTRUCTION & WATER MAIN
Project Description: This project is for the street reconstruction and water main installation on Cruz Drive from Washington Street to Mattes Drive, James Drive from Willard Drive to Mattes Drive and Willard Drive from Cruz Drive to Andre Street. The project scope includes, but is not limited to crushing & shaping of bituminous pavement, storm sewer modifications, removal/replacement of concrete curb and driveway approaches & placement of new bituminous pavement and installation of water main.Detours/Traffic Control: Roads closed to thru-traffic.Project Status: Grading for HMA Paving. Paving is tentatively scheduled for 10/3.Est. Completion Date: September 19, 2025
Swede Avenue Improvements
Project Description: This project is for the street reconstruction of Swede Avenue from Ashman St. to Wheeler St. The project scope includes, but is not limited to aggregate base removal/replacement, storm sewer modifications, removal/replacement of concrete curb and driveway approaches & placement of new bituminous pavement and installation of water main.Detours/Traffic Control: Open to traffic.Project Status: Punch list in progress.
Est. Completion Date: September 5, 2025
2025 MILL & OVERLAY PROGRAM
Project Description: This project is for cold milling & bituminous pavement overlay on various streets (see below) throughout the city, as well as replacement of concrete curb & gutter, sidewalks, ramps and drives.
Major Streets
Wackerly Street: Jefferson Avenue to Swede Avenue
Commerce Drive: Jacobs Drain to Jefferson Avenue
Local Streets
Plymouth Street: Swede Avenue to Blossom Circle Autumn Ridge Circle N.: Plymouth Street to End
Autumn Ridge Circle S.: Plymouth Street to End Trailwood Circle S.: Plymouth Street to End
Trailwood Circle N.: Plymouth Street to End Trailwood Circle E.: Plymouth Street to End
Wild Pine Court N.: Plymouth Street to End Wild Pine Court S.: Plymouth to End
Scenic Drive: Wildflower Lane to Woodview Pass Inverness Circle: Scenic Drive to End
Tennis Court: Scenic Drive to end Wimbleton Court: Scenic Drive to End
North Parkway: Dyckman Road to Crescent Drive Crescent Drive: Meadowbrook Drive to End
Berkshire Court: Crescent Drive to End Bond Court: Crescent Drive to End
Sherwood Court: Crescent Drive to End Bristol Court: Crescent Drive to End
Roanoke Court: Crescent Drive to End Wildwood Street: Swede Avenue to Lamplighter Lane
Lamplighter Lane: Candlestick Lane to End Candlestick Lane: Lamplighter Lane to End
Tiffany Lane: Candlestick Lane to End Lantern Lane: Candlestick Lane to End
Bloomfield Drive: Candlestick Lane to Lantern Lane Bloomfield Court: Bloomfield Drive to End
Applewood Road: Sugnet Road to Valley Drive ** Additional streets as determined by City
Detours/Traffic Control: None at this time.Project Status:Milling Area "E" Plymouth St Subdivision: 10/9 & 10/10
Paving Area "E": 10/13 & 10/14
Milling Area "F" Crescent Drive Subdivsion: 10/14 & 10/15
Paving Area "F": 10/16 thru 10/18
Milling Area "G" Applewood: 10/20
Paving Area "G": 10/21
Est. Completion Date: October 31, 2025
Project Description: This project is for the street reconstruction on Plainfield St. from Westbury Dr. to Mason St., Forestwood Ct., Lund Dr. from Burlington Dr. to Plymouth St., Chatham Ct. and Shawnee Ct. The project scope includes, but is not limited to crushing & shaping of bituminous pavement, removal/replacement of concrete curb, sidewalk ramps and driveway approaches & placement of new bituminous pavement.Detours/Traffic Control: Closed to Thru-traffic.Project Status: Grading aggregate base course. Paving scheduled for 10/8.Est. Completion Date: October 19, 2025
Sidewalk Replacement Program No.1
Project Description: The project scope includes removal and replacement of sidewalks and sidewalk ramps, at the following locations:
East and West Collins Streets from Adelaide Street to George Street, Ivy Lane from Dina Street to Rapanos Drive, and Dina Street from Wyllys Street to Rapanos.Detours/Traffic Control: N/AProject Status: Sidewalk replacements are complete on Collins, restoration in progress. Removals are in progress on Dina St. & Ivy Ln.Est. Completion Date: October 31, 2025
2025 EASTMAN AVENUE RECONSTRUCTION
Project Description: This project is for the street reconstruction from the northerly driveway of the Midland Mall to Commerce Drive. The project scope includes, but is not limited to, crushing & shaping of bituminous pavement, storm sewer modifications, removal/replacement of concrete curb and driveway approaches and placement of new bituminous pavement.Detours/Traffic Control: One lane of northbound, one lane of southbound and one center left turn lane shall be maintained on Eastman Ave. for the entire duration of construction, with the exception of the paving operation, where the center left turn lane may be eliminated.
Westbound traffic on Joe Mann Blvd. shall be detoured via Elisenal Dr. and Commerce Dr. Eastbound traffic on Joe Mann Blvd. shall be maintained.Project Status:Concrete curb & gutter in progress.Est. Completion Date: October 31, 2025
Indian & Buttles (MDOT)
Project Description: The Michigan Department of Transportation (MDOT), in partnership with the City, will relocate overhead power and communication utilities from power poles to underground conduits, along Buttles St. from Jerome St. to State St. Construction is expected to begin August 25, 2025 and last until March 31, 2026.
This work is being completed in preparation for MDOT�s reconstruction of Indian St. & Buttles St., expected to begin in the spring of 2026. Additional details will be communicated when they become available.Detours/Traffic Control: There will be a lane closure on Buttles from 400ft west of Jerome St. through State St., along with intermittent closures of Ashman, McDonald, Rodd, Townsend, Cronkright, George and State Streets. The sidewalk on the south side of Buttles St. will be closed to pedestrian traffic throughout this project, with pedestrian traffic detoured to the north side of Buttles St. Project Status:Est. Completion Date: March 31, 2026
2025 PERRINE ROAD RECONSTRUCTION & WATER MAIN
Project Description: This project is for the street reconstruction on Perrine Road from Airport Road to E. Letts Road, and water main installation on Perrine Road from Letts Street north to Winding Creek Drive. The project scope includes, but is not limited to crushing & shaping of bituminous pavement, removal/replacement of concrete curb, sidewalk ramps and driveway approaches & placement of new bituminous pavement and installation of water main.Detours/Traffic Control: Northbound traffic shall remain open for the duration of construction. Southbound traffic detoured via Dublin Rd., please follow posted detour.Project Status: Ditching and culvert installations are in progress.Est. Completion Date: October 31, 2025
UPCOMING CONSTRUCTION
No Upcoming Construction
Map of Midland Construction Areas
Click on the colored lines in the map below to find details on the proposed, active, and completed construction projects in the city.